SNOWSHAGAL / RESEARCH NO.08
2026.10.03
SNOWSHAGAL
Investment Research
NO.082026.10.03
Engines · Ships · Data centers

The Engine Is
the Bottleneck

Shipboard generators meet
data-center power plants

As grid connections and gas turbines stretch out, some on-site power demand is shifting to four-stroke engines · In Korea, part of that demand runs into ship-generator orders on the same medium-speed manufacturing and test base

GE Vernova heavy-duty gas turbines · new slots2031 delivery yeardelivery · 53 GW backlog + 63 GW of slot reservations
HD Hyundai HiMSEN engine capacity3.0→7.2 GW2025→2030 · land-based power 0.7→4.0 GW · Shinhan Securities / SK Securities
Korea + China merchant-ship contracts · through end-August · DS Investment & Securities173 m DWTabout 90% of the 2007 full-year record of 194m DWT
Cover · conceptual image · not an actual facilityStart reading ↓
Before you readPage 00
Where two demands meetFirst, know the engines

Three Ways to Make Power.
One Point of Overlap

U.S. data centers can wait years for a grid connection, while new heavy-duty gas-turbine slots are already pushed out to 2031 deliveries. In the gap, some on-site generation demand is moving to four-stroke gas engines. Korean engine makers entered this cycle with thick marine order books from the shipbuilding boom. On parts of their medium-speed four-stroke lines—and in the test and component supply chains around them—ship-generator orders now meet land-based power orders. This report follows where those two demand pools actually collide, and who gets to book the revenue when capacity is scarce.

Two-stroke low-speed marine engine
SHIP PROPULSION

Two-stroke low-speed engines

  • Turn the propellers on large merchant ships
  • Hanwha Engine · HD Hyundai Heavy Industries · HD Hyundai Marine Engine
  • No direct overlap with data-center power
WHERE THE TWO DEMAND POOLS MEET
Four-stroke medium-speed engine genset
GENSET · POWER PLANT

Four-stroke medium- and high-speed engines

  • Shipboard gensets that make electricity on board
  • On-site data-center power plants (multiple units from a few MW to roughly 20 MW each)
  • Medium-speed: Wärtsilä · HD Hyundai (HiMSEN) · Hanwha Engine · High-speed: Caterpillar · INNIO · Cummins
Cutaway gas turbine
GAS TURBINE

Gas turbines

  • Aeroderivative units · heavy-duty combined cycle
  • GE Vernova · Siemens Energy · Mitsubishi Heavy Industries · Doosan Enerbility
  • The longest equipment-delivery queue

Two-stroke marine propulsion engines and four-stroke power-generation engines are different products, so we do not add their manufacturing capacity together.

What this report means by the “engine bottleneck”SCOPE
IN SCOPE
  • Parts of the assembly, testing, and component supply chain for four-stroke medium-speed engines
  • Shipboard auxiliary generation ↔ data centers and land-based power
  • Production slots · lead times · allocation by delivery year
OUT OF SCOPE
  • The entire market for two-stroke main propulsion engines on large merchant ships
  • The full market for high-speed gensets from Caterpillar, INNIO, Cummins, and others
  • The gas-turbine bottleneck as a whole

Hanwha Engine’s estimated 2027 headroom for data centers: about 360 MW (SK Securities) · a single 400 MW project delivered in one year would be large enough to force a rethink of marine allocation

Published 2026.10.03 · Information checked through 2026.10.02 20:00 KST · Overseas-company figures use each company’s latest reported period: 2Q26, except Siemens Energy FY26 Q3 and Mitsubishi Heavy Industries FY26 Q1 · Korean broker estimates and manufacturer claims are labeled as such · Figures we could not verify in public materials remain flagged in the source ledger.

Turbines sold outPage 01
WhyWhy data centers are turning to on-site power

When Turbines Backed Up,
Engines Moved In

Grid connection · equipment delivery · commercial operation run on three different clocks
Oblique view of rows of gas-engine generating units beside a data-center building
2031 delivery yearGE Vernova heavy-duty gas turbine · delivery if a new slot is booked today
An on-site power plant built on the data-center campus. Identical engines are installed in parallel, with more units added as demand grows · conceptual image · not an actual facility

A U.S. data-center project can run into three separate waits: the wait to connect to the grid, the wait to receive its own generating equipment, and the wait until every supporting system is ready for commercial operation.

The first queue is already long. ERCOT, the Texas grid operator, has more than 438,000 MW of large-load interconnection requests in its pipeline, and 89% of that volume is data centers.1 SK Securities estimates that a U.S. AI data center can take about five years from applying for grid interconnection to commercial operation.2 The LBNL figure often cited alongside it—“more than five years,” with a 2025 median of 61 months—measures interconnection time for generation and storage projects. It is not the same statistic as connecting a load such as a data center.3

That is why developers are building power plants on site. In a forecast DS Investment & Securities cites from BCG and Goldman Sachs, on-site generation rises from 10% of U.S. data-center power in 2026 to 30% by 2030.4 Then the second queue begins. Book a new GE Vernova heavy-duty gas-turbine slot today and the delivery year is 2031.5 In Korea, Doosan Enerbility has booked 12 cumulative orders for 380 MW-class gas turbines from U.S. customers. The latest seven are scheduled to ship at a pace of one per month starting in May 2029.6

Backlog at the Big Three gas-turbine makers · GWFIG 01-1 · end-June 2026
GE Vernova 53 firm backlog + 63 slot reservations (hatched)
116
Siemens Energy gas-turbine backlog
69
Mitsubishi Heavy Industries heavy-duty gas turbines · 23 a year earlier
35
0255075100125
Hatching denotes slot reservations —production positions held before a firm order · Reporting bases differ across the three companies, so this is not a league table · Siemens Energy lead times exceed three years · GE targets at least 125 GW of backlog plus reservations by year-end.5, 7, 8

Engines come with a shorter queue. SK Securities puts four-stroke lead times at one to two years for high-speed engines and two to three years for medium-speed engines.2 Wärtsilä’s 412 MW Ohio engine plant, ordered in April, is targeting commercial operation in early 2028—roughly two years from order to start-up.9 Not every way around the grid requires a new engine. On Oct. 1 in Japan, JERA, Dell, and RHAELM signed an MoU to place up to 400 MW of AI infrastructure at JERA’s existing Chiba thermal plant and use plant power behind the meter. They say the structure can come online years ahead of a conventional grid-connected development, with operation targeted around 2028.10 Putting a data center next to an existing power asset is another answer to the same grid bottleneck.

Equipment delivery lead time · yearsFIG 01-2 · SK Securities
Heavy-duty gas turbine
5~6
Aeroderivative gas turbine only an upper bound disclosed
up to ▸
≤3
Four-stroke medium-speed engine
2~3
Four-stroke high-speed engine
1~2
02468 years
Equipment-delivery lead time only · excludes installation, commissioning, and permitting · The same SK Securities report also describes four-stroke engines as an “18–24 month” category.2

Getting the engine is not the same as getting power

Faster equipment does not automatically mean an earlier power-on date. The gas pipeline, emissions permits, and electrical systems all have to be ready before commissioning can begin. At Oracle’s Project Jupiter in New Mexico, pipeline completion slipped to February 2027 and an air permit for the fuel-cell system had not been issued, prompting Oracle to notify the developer of force majeure.11, 12 Oracle says the project remains on schedule.12

What has to finish before an on-site plant can switch on · workstreams that run in parallelFIG 01-3 · schematic
Engine manufacture and delivery
Gas supply infrastructure / pipeline
Air and noise permits
Electrical systems and power conditioning
Commissioning and commercial operation
Not an actual project schedule · hatching shows how delays can appear · the last workstream to finish sets the commercial-operation date.
10.01 KST · a “generator-to-chip” partnership

A faster engine delivery alone does not pull the date forward

Wärtsilä
Schneider Electric
Stanley Consultants

The companies announced a U.S. data-center “Generator-to-Chip” collaboration: Wärtsilä provides modular engine power plants; Schneider provides electrical equipment, automation, and power management; Stanley provides design, permitting, construction management, and commissioning oversight. The pitch is to design the pieces together from the start and compress schedules versus the traditional sequential model. No firm capacity or quantified schedule saving was disclosed.13

The collaboration goes straight at the problem that shortening generator lead time alone may not move commercial operation forward. The critical constraint can migrate from engine procurement to the integration of electrical design, permitting, and commissioning.

PAGE 01 On-site generation is an attempt to bypass the first queue. Engines shorten the second. The third queue remains.

NEXT02 When does an engine win?
Choosing a machinePage 02
HowWhen does an engine win?

Engines, Aeroderivatives,
or Combined Cycle?

Three large gas-based options are in scope · once the comparison is put on the same footing, the winner changes with the use case
Rows of medium-speed gas engines inside an engine power plant
Inside an engine power plant. Multiple engines—from a few MW to roughly 20 MW each—are installed as modular blocks · conceptual image · not an actual facility

Fuel cells, diesel generators, and rental power are also options for on-site supply. This report focuses on three large gas-based alternatives: banks of four-stroke medium-speed gas engines, banks of aeroderivative gas turbines, and—if the schedule allows it—a large combined-cycle plant. Break the choice into four questions and each option wins under different conditions.

① Time to first power

Separate equipment lead time from installation time

Medium-speed gas engines

Equipment lead time: 2–3 years · multiple units can be installed in sequence, allowing partial operation to start sooner.2

Aeroderivative gas turbines

Equipment lead time: up to 3 years · GE says packaged units can be installed in under 30 days.2, 14

Large combined cycle

Heavy-duty turbine lead time: 5–6 years · then add construction of the heat-recovery steam generator (HRSG) and steam turbine.2

② Efficiency and fuel cost

Distinguish a single machine from the whole plant, and simple cycle from combined cycle

Medium-speed gas engines

Simple-cycle efficiency: 45–48% (Wärtsilä data).2

Aeroderivative gas turbines

Simple-cycle efficiency: 40–44% (same source).2

Large combined cycle

Plant efficiency above 60% · the lowest fuel use of the three.2

③ Load following and expansion

Separate the behavior of one machine from a plant made up of many machines

Medium-speed gas engines

Turn individual units on and off while keeping plant efficiency around 45–48% across a 20–100% plant load · add capacity in increments from a few MW to roughly 20 MW.2

Aeroderivative gas turbines

A 50 MW-class unit is about 25% efficient at 30% load · GE cites a five-minute fast start.2, 15

Large combined cycle

Capacity comes in large blocks · cold starts take hours.2

④ Redundancy and site footprint

Compare at the same required capacity and reliability target

Medium-speed gas engines

Smaller unit size keeps the cost of one spare unit lower · less high-temperature derating and lower water use.2

Aeroderivative gas turbines

Tens of MW per unit · the spare-capacity percentage depends on unit count.

Large combined cycle

Large unit size makes redundancy more expensive · bigger footprint and typically cooling-water needs.2

The efficiency figures are manufacturer-derived data from Wärtsilä cited by SK Securities · actual performance varies with plant configuration and operating conditions.

The weight of one spare unit (N+1) · when 100 MW is requiredFIG 02-1 · arithmetic example
100 MW × 1 unit + 1 spare
100% spare
25 MW × 4 units + 1 spare
25% spare
10 MW × 10 units + 1 spare
10% spare
Spare-capacity ratios under a hypothetical like-for-like setup · actual cost ratios depend on shared balance-of-plant and equipment pricing · the point is simply that smaller modules can reduce the redundancy burden.

UPS takes the first hit from GPU volatility

AI compute loads swing on a millisecond timescale. The first device to absorb that shock is the UPS.16 An engine or aeroderivative turbine reaching full output within minutes is a statement about minute-scale load following; power-quality problems live on a much faster clock. That is why on-site plants pair generators with power-conditioning equipment such as UPS systems.

Minutes
Gas engines · turbines

Baseload supply and load following · output adjusted by starting and stopping units.

Seconds to milliseconds
Power conditioning · UPS

Absorbs fast swings and momentary outages · the Bergen–Crusoe contract also includes separate power-conditioning equipment.17

Load
GPU servers

Synchronized training cycles can move demand by tens of MW in a flash.2

CASE · What one buyer actually procured

Crusoe bought both engines and turbines

2024.12 · 2025.06
GE Vernova

Aeroderivative LM2500XPRESS gas turbines for data centers: 29 units cumulatively, nearly 1 GW · GE emphasizes five-minute fast-start capability.15

2026.06
Bergen Engines

Gas engines: about 750 MW · roughly 438 MW is under firm contract (27 × 12.5 MW + 20 × 5 MW); the remaining 310 MW is under letters of intent · phased deliveries to multiple U.S. sites through 2027 · intended for continuous on-site baseload generation · paired with power-conditioning equipment.17

The same buyer is procuring both engines and turbines · not all announced capacity is a firm order.

NEXT03 How firm is the marine queue?
The sea queuePage 03
WhoHow firm is the marine queue?

The Shipping Queue
Was There First

Korean and Chinese merchant-ship contracts through August already equal roughly 90% of the 2007 full-year record · Chinese yards are buying Korean engines too
A crane lowers an engine module onto an LNG carrier under construction at a shipyard
173 m DWTKorea + China merchant-ship contracts · through end-August · DS Investment & Securities · about 90% of the 2007 full-year record
A merchant ship under construction. Alongside one or two two-stroke main propulsion engines, several four-stroke generator engines make electricity on board · conceptual image · not an actual facility

The engine factories were busy with ships before data centers came calling. Merchant-ship contracts at Korean and Chinese yards reached 173 million DWT through end-August—about 90% of the 194 million DWT full-year record set in 2007.18 DS Investment & Securities estimates that, if the current pace holds, the full-year total could reach 260 million DWT and surpass 2007.18

Korea + China merchant-ship contracts · 100m DWTFIG 03-1
2007 full year · record high
1.94
2026 through end-August
1.73
2026 full year · DS estimate
2.6
01.02.03.0
DS Investment & Securities · 2026 full-year figure is an estimate (hatched) assuming the current pace continues through the remaining four months · In DS’s chart, the 2024 full-year total was also only modestly above the end-August cumulative figure.18

When ships sell, engines follow. A large merchant ship typically carries one or two two-stroke propulsion engines plus several four-stroke generator engines for onboard electricity. Clarksons Research puts the global orderbook at 216.43 million CGT at end-August, with China at 67% and Korea at 18%. The Newbuilding Price Index stood at 186.34.19

Why Chinese shipyards are buying Korean engines

According to DS Investment & Securities, Chinese yards expanded dock capacity quickly, but domestic engine production failed to keep up. Scarce Chinese engine slots were allocated first to state-owned yards, pushing private yards with delivery schedules to meet toward Korean suppliers.18 In 2025, Korean-engine orders from private Chinese yards topped KRW 900bn, up more than 45% year on year. DS discusses the trend alongside two-stroke propulsion-engine market share. The demand that directly touches four-stroke capacity is the generator-engine package—multiple units per vessel.18

Chinese shipyards buying Korean engines · 2025 order valueFIG 03-2 · DS Investment & Securities table
ShipyardKorean-engine orders
Jiangsu New YangziKRW 629.2bn
New TimesKRW 216.0bn
Zhoushan ChanghongKRW 84.2bn
Qidong XiangyuKRW 35.8bn
DS Investment & Securities, “Engines: The Semiconductors of the Sea” · values converted from KRW bn to KRW 100m in the source table, and shown here in English units · based on disclosed orders won by Korean engine makers, so it may not capture every order.18

Of the 15 contracts HD Hyundai Marine Engine won in the first half of this year, 12 came from Chinese shipyards,20and broker analysis published at end-August said China’s share of Hanwha Engine’s order backlog had risen from 33% to 49%.21 Marine orders for Korean engine makers are coming not only from Korean shipyards, but also from Chinese yards short of engine slots.

NEXT DEMAND · the next swing factor for marine orders

Dec. 4 · the IMO Net-Zero Framework returns to the table

The International Maritime Organization (IMO) postponed adoption of the Net-Zero Framework (NZF), its carbon-pricing regime for international shipping, for one year in October 2025 by a 57–49 vote.22 The discussion is scheduled to run through Nov. 30–Dec. 3 MEPC 85 and resume in a special session on Dec. 4, with the date to be confirmed at MEPC 85.23 The September intersessional working group also ended without agreement, while the United States and Saudi Arabia continued to oppose the framework.24

DS Investment & Securities calculates that even if the charge were implemented at half the proposed level, cumulative carbon costs over 20 years could reach 20–30% of a new vessel’s price, assuming USD 100–130 per tonne and no discounting.18 Treat that as an order-of-magnitude gauge of the regulation, not as an investment-economics model for an individual ship. If the NZF is adopted, vessel classes where dual-fuel (DF) penetration remains below 1%—including VLCC and small-to-mid-sized container ships—are cited as the next candidates for conversion;18if the framework is delayed again, the incentive weakens.

Adoption strengthens the incentive to move to DF engines; another delay weakens it · the next swing factor for marine-engine demand.

PAGE 03 Korean and Chinese merchant-ship contracts had already reached 173 million DWT by August, and private Chinese yards are also sourcing Korean engines. The part that meets data-center demand is the four-stroke generator engine—several units on each ship.

NEXT04 Where the production bottleneck really overlaps
Where it actually bindsPage 04
WhereWhere the production bottleneck really overlaps

Don’t Watch the Factory.
Watch the Line.

Overlap comes in degrees · the bottleneck sits in four-stroke medium-speed lines and the testing and component supply chains around them
Two technicians inspect a medium-speed engine on a factory test bed
Once assembly is complete, an engine goes through load testing on a test bed before shipment. Where marine and power-generation engines share those facilities, the two order books must divide the same test hours · conceptual image · not an actual facility

Wärtsilä manufactures every engine in its portfolio at the Sustainable Technology Hub in Vaasa, Finland. In two announcements, in February and May, the company said it would expand the plant and related supply-chain capacity by 65% versus 2025. Both announcements cited demand from Energy and Marine.25 That is a company-level example of marine and power-generation orders meeting on the same manufacturing base.

Wärtsilä has also described how it allocates that capacity. In a summary of its CEO strategy call published Sept. 29, the company said data centers account for less than half of its Energy equipment backlog. It does not sign slot-reservation agreements with individual customers; instead, it allocates capacity to firm orders based on commercial opportunity, strategic priority, customer relationships, and geographic diversification, while continuing to serve both Energy and Marine customers.26 Data centers have not taken over the factory. Firm orders from two end markets are sharing the production clock.

But “made by the same company” does not, by itself, prove that two products are fighting for the same production hours. There are levels of overlap.

Three levels of overlapFIG 04-1
LevelWhat it showsWhat it does not prove
Same companyThe company has exposure to both marketsThe two products compete for the same production time
Same siteThey may share land, labor, and some infrastructureThey share assembly, testing, and critical machining equipment
Same process / equipmentProduction allocation can genuinely collideThat specific process is currently full

On this test, two-stroke marine propulsion engines and data-center engines overlap only at the company level. The real collision is in four-stroke medium-speed lines that serve both shipboard generation and power plants. Most data-center engine orders, meanwhile, are high-speed gensets from Caterpillar, INNIO, Cummins, and others; those do not share marine-engine lines.2

Where does the overlap sit by company?FIG 04-2
Company · siteWhat it buildsWhere data-center demand can overlapUtilization / expansion signal
HD Hyundai Heavy Industries
Ulsan · new Onsan plant
Large two-stroke marine engines · HiMSEN four-stroke enginesHiMSEN four-stroke assembly and testing, until the new plant comes onlineFILING Engine utilization 113% (2Q · entire Engine & Machinery division)27
HD Hyundai Engine
Yeongam
Power-generation engines up to 10 MW, among othersSmaller-scale power generationBROKER ESTIMATE Expansion to 1.0 GW by 2027 (DS)18
HD Hyundai Marine Engine
Changwon · former STX Heavy Industries
Two-stroke marine engines · turbochargers · crankshaftsComponents such as turbochargers used in four-stroke enginesBROKER ESTIMATE Turbocharger utilization forecast at 100% in 2H from marine volume alone (DS)18
Hanwha Engine
Changwon · former HSD Engine
Two-stroke marine engines · four-stroke medium-speed engines (new 900 MW/year line)Allocation of four-stroke line between shipboard generation and land-based powerBROKER RESEARCH Two-stroke slots sold out through 2028 · 1H26 utilization about 96% (DS chart)18
(COMPARISON) Wärtsilä
Vaasa, Finland
All engines in the portfolioMarine and power-generation engines made at the same factoryCOMPANY DISCLOSURE Planned +65% capacity versus 202525
Company-wide or segment-wide metrics do not prove that a specific line is full · predecessor entities and site locations for HD Hyundai Engine and HD Hyundai Marine Engine follow published reports.28

HD Hyundai · big contracts versus the new plant’s start date

HD Hyundai Heavy Industries signed power-engine contracts in April with U.S.-based Aperion Energy Group for 684 MW (KRW 627.1bn) and in August with Corban Energy for 1,000 MW (KRW 956.0bn).29, 30 Together, roughly 1.7 GW of contracted volume is far above the company’s historical annual land-based power sales, described by SK Securities as only 0.2–0.3 GW per year.2 But both contracts are spread across several years, and the new Onsan plant in Ulsan that is meant to absorb the growth is not scheduled for completion until May 2028.31 The new plant includes assembly and commissioning facilities plus crankshaft machining and block-casting equipment. Reports relaying company comments say the main Ulsan plant will focus on marine engines, while the new plant and the Yeongam site will serve land-based power.28, 32 To say contracts are outrunning expansion, annual delivery volumes and annual capacity have to be put on the same timeline.

2027–2030 · new plant, capacity, and delivery scheduleFIG 04-3 · HD Hyundai land-based power
Item2027202820292030
Onsan new plant FILINGConstruction starts in 1QCompletion in May · 3 GW/year installed capacity comes onlineRamp-up (initial utilization about 30%, DS estimate)HiMSEN total-capacity target: 7.2 GW
Land-based power capacity BROKER ESTIMATEabout 1.0 GWabout 1.45 GWabout 3.1 GW4.0 GW
AEG 684 MW deliveries BROKER RESEARCH–11 units (about 0.23 GW)11 units11 units
Corban 1,000 MW FILINGContract period 2026.08–2030.07 · annual delivery schedule not disclosed
  1. 2027Capacity about 1.0 GW · Onsan construction starts in 1Q
  2. 2028About 1.45 GW · Onsan completes in May (3 GW/year equipment base) · 11 AEG units (about 0.23 GW)
  3. 2029About 3.1 GW · utilization ramps (initially about 30%, DS estimate) · 11 AEG units
  4. 20304.0 GW · HiMSEN total-capacity target 7.2 GW · 11 AEG units
  5. Corban1,000 MW · contract period 2026.08–2030.07 · annual delivery schedule not disclosed
Capacity figures are approximations read from a DS Investment & Securities chart · completion is not the same as normalized utilization, and reports citing “7.2 GW in 2028” appear to mix the plant-completion date with the later total-capacity target · AEG’s annual unit schedule appears only in SK Securities research, while the filing gives a contract period of 2026.04.21–2030.10.21 · Corban has disclosed only the contract period, so the two contracts alone are not enough to determine whether annual capacity is exceeded.2, 18, 29, 30, 31, 32

On the table, AEG alone requires only about 0.23 GW per year—a slice of estimated land-based capacity in those years. Whether a real bottleneck emerges depends on the undisclosed Corban delivery profile and additional orders.

Hanwha Engine · a large project versus annual headroom

Hanwha Engine completed a new four-stroke medium-speed line in Changwon in August with annual capacity of 900 MW, or 180 units at 5 MW each.33 SK Securities estimates that about 60% of the line will be used for marine applications in 2027, leaving roughly 360 MW of headroom for data centers. Data-center buyers are typically looking for projects in the 250–400 MW range.2 Annual headroom and total project capacity are not the same unit of time. The answer changes with how many years the deliveries are spread across.

If Hanwha wins a 400 MW project · using about 360 MW of estimated 2027 headroomFIG 04-4 · arithmetic example
Delivery profileAnnual volume requiredVersus annual headroom
All in one year400 MWAbove headroom · marine allocation would have to move
Split over two years200 MW per yearWithin headroom · but leaves less room for other data-center orders
Split over three yearsabout 133 MW per yearWithin headroom
Illustrative arithmetic using SK Securities’ estimated 60:40 marine/data-center split applied to 900 MW of annual capacity · Hanwha Engine’s power-generation product still faces an Everllence 35/44G licensing and certification schedule, and as of Oct. 2, 2026 no firm data-center order had been publicly reported.2, 33
PAGE 04 · TAKEAWAY

Demand for shipboard generator engines and data-center medium-speed four-stroke engines overlaps in parts of the manufacturing and testing base and in the component supply chain.

The annual delivery plan for this specific line matters more than a company-wide utilization figure. HD Hyundai is trying to separate the two demand pools with a new plant; Hanwha Engine has to divide a limited four-stroke capacity pool between marine and power-plant customers.

NEXT05 Who keeps the economics?
Who keeps the marginPage 05
WhatWhere does the incremental order turn into profit?

Today’s Margin. Tomorrow’s Order.
Then Comes Service.

Current earnings · economics of new orders · aftermarket revenue arrive at different times and can accrue to different companies

An engine maker’s reported earnings mix three different clocks. Today’s margins reflect orders won in the past and delivered now. Data-center orders booked this year will turn into revenue over several years according to each contract’s delivery schedule. Bergen–Crusoe deliveries run through 2027, while some large Korean contracts ramp more meaningfully from 2028 onward.2, 17 Service revenue comes later still—and sometimes lands at a different company.

① Today’s earnings · delivery of old orders and product mix

Operating margin at HD Hyundai Heavy Industries’ Engine & Machinery division rose from 18.3% in 2025 to 24.8% in 2Q26,27while HD Hyundai Marine Engine rose from 18.9% to 24.4% over the same period.34 Hanwha Engine’s backlog grew from KRW 2.5472tn at end-2023 to KRW 5.9789tn at end-June 2026, with dual-fuel (DF) engines accounting for 83%.35 HiMSEN land-based power sales had been only 0.2–0.3 GW per year (SK Securities),2 so it is reasonable to read most of those margins as coming from marine-engine deliveries. The Korean data-center engine contracts signed this year are either not yet being delivered or are still in early stages, making them unlikely to be the main source of 2Q margins.

HD Hyundai Heavy Industries · Engine & Machinery operating margin · %FIG 05-1
18.3
21.1
24.8
20251Q262Q26
Annual and quarterly figures shown together to indicate direction · axis starts at zero.27

Hanwha Engine’s average selling price per engine rose from roughly KRW 7.0bn in 2Q24 to about KRW 10.4bn in 1Q26, based on a DS Investment & Securities chart.18 That figure also reflects a richer mix of higher-priced DF engines. Reading it as a like-for-like price increase of the same magnitude would overstate the evidence.

② New orders · price and delivery timing

Wärtsilä provides the clearest direct datapoint on the economics of new orders. Since early 2025, its Energy backlog has more than doubled, while the gross margin embedded in the Energy equipment order book has improved by more than 500 basis points.36 That is margin on orders to be delivered in the future, not margin already realized. In the same release, Wärtsilä said equipment delivery periods continue to extend, pushing revenue from the existing backlog further into the future.36 That is why backlog can grow faster than near-term revenue. GE Vernova management has also said pricing on new gas-turbine orders is running above 4Q25 levels.37

New orders are also appearing outside the engine OEMs. On Oct. 1, Canada’s Enerflex won a contract from a North American data-center developer to design, engineer, fabricate, and assemble roughly 450 MW of behind-the-meter natural-gas generation. Deliveries start in 2027 and finish in 2028; Enerflex approved about USD 15m of 2026 capex and a further roughly USD 85m, mostly for 2027.38 This is a separate datapoint from engine-OEM production slots. What it does show is that on-site power demand continues to convert into real contracts—and that system integrators are also adding capacity, so the supply side has begun to respond.

Technician servicing an engine with the cylinder-head cover open
A power-generation engine under maintenance. Data-center engines can run nearly continuously, shortening service intervals versus marine duty · conceptual image · not an actual facility

③ Then comes service · the installed engine base

SK Securities estimates that data-center engines run nearly year-round, shortening the maintenance cycle to about three years versus five years for marine engines, and that over a 25-year operating life service revenue could equal roughly 2.5× the original engine sale.2 Who owns that revenue differs by company. HD Hyundai Marine Solution signed an MoU with AEG in May to pursue long-term maintenance and operations for the 33 engines HD Hyundai Heavy Industries is supplying to AEG. It is not yet a signed long-term service agreement.39 For marine engines, Hanwha Engine offers LTSA coverage that can run for the life of the engine and has signed a five-year agreement with Pan Ocean.40 For licensed power-generation models, the split of service rights has to be checked contract by contract.

Who does what in data-center powerFIG 05-2
CompanyRoleStage secured
HD Hyundai Heavy IndustriesBuilds HiMSEN engines · contracting party for equipment supplyAEG 684 MW (filing · 2026.04–2030.10) · Corban 1,000 MW (2026.08–2030.07)29, 30
HD Hyundai Marine SolutionService and operations (LTSA · O&M)MoU for maintenance of 33 AEG engines (2026.05) · not a firm service contract39
HD Hyundai Marine EngineTwo-stroke marine engines · components including turbochargersNo reported direct data-center contract
Hanwha EngineBuilds two- and four-stroke engines · pursuing a licensed power-generation productNo reported firm data-center order as of Oct. 233
WärtsiläEngine manufacturing and serviceGross margin in the Energy equipment order book improved by more than 500 bp36
Equipment orders and service contracts must be checked separately · similarly named entities—HD Hyundai Heavy Industries, HD Hyundai Marine Engine, and HD Hyundai Marine Solution—play different roles.
NEXT06 The equipment can arrive—and the project can still stall
Beyond the equipmentPage 06
RulesWhat can still bottleneck after the equipment arrives?

Permits. Gas.
Grid Rules.

Policy is widening the menu for on-site power · it does not guarantee demand for any specific engine
Gas-pipeline construction and transmission towers crossing a plain at dusk, with a data center in the distance
What remains after the equipment arrives: the pipe that brings in fuel, the grid connection, and the rules that govern both · conceptual image · not an actual facility

U.S. power-market rules are moving toward opening a path for data centers to bring their own generation (BYOG). What is widening is the ability to choose on-site power. There is no rule telling developers to use gas engines. The direction is clear; the rulebook is still moving.

In December 2025, the Federal Energy Regulatory Commission (FERC) directed PJM, the largest U.S. grid operator, to create a new transmission service for large loads co-located with generation.41 In January 2026, the PJM board outlined a path for large loads to bring new generation with them,42while Texas approved Batch Zero in June to review large loads of 75 MW or more in a coordinated process.1 More of the cost is shifting to the data center as well. In July, the Oregon Public Utility Commission approved a 29.7% rate increase for PGE data centers and other large loads.43

The latest move came on Sept. 29. FERC accepted PJM’s Reliability Backstop Procurement proposal, but suspended its effective date for five months, until Feb. 28, 2027, subject to refund conditions and the outcome of further proceedings. Questions including cost allocation and collateral moved into additional proceedings, and PJM did not launch the procurement it had planned to begin on Sept. 30.44 In separate concurrences, Commissioners Rosner and See emphasized a cost-causation principle: new large loads such as data centers should bear the costs they create rather than shifting them to existing customers.45 Those are individual commissioners’ concurrences, not a rate rule, and they do not require on-site generation. But they are a signal that large loads may be asked to shoulder power-supply costs more directly.

The path for large loads to bring their own new capacity is also becoming more concrete. On Aug. 13, PJM filed BYONC (Bring Your Own New Capacity) and an Interim Resource Adequacy Service (IRAS) with FERC, requesting an Oct. 12 effective date. The proposal would allow qualifying large new loads that bring new generation to avoid first-in-line curtailment during emergencies. FERC approval is still pending.46

What can still hold up a projectFIG 06-1
ConstraintRecent case
Air permittingVirginia · data-center air-permit applications filed from July 1 onward must meet Tier 4-equivalent or tighter emissions limits for each generator set under Va. Code § 10.1-1322.6; the statutory gen-set definition does not restrict fuel type47 · A September executive order removed new data centers of 25 MW or more from fast-track permitting and state support and ordered a review of emergency-generation equipment; it is not a ban on gas generation48
Gas supplyOracle Project Jupiter, New Mexico · pipeline completion delayed to February 2027 · force-majeure notice issued11
Fuel cells need permits tooSame project · air permit for fuel cells not yet issued · permitting was paused and later resumed4, 11
State-level moratoriumNew York · state environmental permitting for data centers of 50 MW or more paused for up to one year from July49

PAGE 06 An engine can be on site and the project can still miss its date if the gas pipeline, air permit, or grid-connection rule is late. Oracle’s Project Jupiter in New Mexico is the live example.

NEXT07 What changes first when supply catches up?
Three clocksPage 07
WhenWhat changes first when supply catches up?

Three
Clocks

Major engine expansions cluster in 2028–29 · gas-turbine market “normalization” is forecast for 2031–32 · engine pricing power may turn first

Almost every major power-equipment supplier is adding capacity. The biggest engine expansions cluster in 2028–29, while the broader gas-turbine market is not expected to “normalize” on lead time until 2031–32. Some individual turbine expansions arrive in 2027–28. That means it is too simple to say engines will loosen first; the better frame is that different parts of the market clear on different clocks.

Who is adding what—and when?FIG 07-1
CompanyPlanTiming
WärtsiläVaasa plant and supply chain +65% versus 20251Q28 (+35%) · 1Q29 (+30%)
CaterpillarLarge reciprocating-engine capacity 3× versus 2024 · 1.5 GW from restarted 10 MW-class medium-speed lineInvestment concentrated in 2027–29 · medium-speed shipments start 4Q26
HD Hyundai Heavy Industries3 GW/year Onsan power-engine plant · HiMSEN 7.2 GWPlant completes May 2028 · 7.2 GW target in 2030
Hanwha Engine900 MW/year four-stroke lineCompleted August 2026
GE VernovaGas-turbine capacity 20 GW/year → 24 GW → 30 GW2028 · 2030
Siemens EnergyHeavy-duty roughly 35 units/year → +15 units · medium-size 80/year → about 100/year2027 · 2028
Mitsubishi Heavy IndustriesGas-turbine capacity to double versus 2024In progress
Doosan EnerbilityGas turbines 8/year → 12/year2028
Highlighted rows are engine makers · units are not comparable and are not added together · 2031–32 gas-turbine supply normalization is an SK Securities forecast.2, 5, 7, 8, 25, 31, 32, 33, 50, 51

SK Securities argues that all major gas-turbine makers are effectively running full, and that even with expansion the market does not normalize until 2031–32.2 Rystad Energy likewise says gas-turbine and reciprocating-engine orders reached about 100 GW in 2025—30% more than OEMs could actually deliver—and that the gap has not yet closed. The same report, however, warns that oversupply risk is building in the 20–50 MW segment as new entrants pile in.52 Meanwhile, major engine expansions begin coming online earlier, in 2028–29. Engine-to-engine competition can intensify before turbine queues clear, changing pricing power sooner. Some competitive supply arrives even earlier: Caterpillar has restarted a 10 MW-class medium-speed gas engine it discontinued in 2022, secured its first order, and plans to ramp to roughly 1.5 GW over 18 months after first shipments in 4Q26.50 In other words, the engine bottleneck may start easing before Korean suppliers finish their own expansions. That is why the expiry date of the bottleneck cannot be read from gas-turbine lead times alone; engine-capacity additions have to be tracked in parallel.

Three clocks that need to be tracked separatelyFIG 07-2
ClockWhat to watchWhen supply rises
New equipment ordersLead time · pricing and economics on new orders · conversion or cancellation of reservationsThis is where growth can slow first—or where pricing can crack first
Installed enginesOperating hours · primary power vs. backup duty · utilizationWhether they keep running after grid or turbine capacity arrives is a separate economic decision
Service businessService-contract attach rate · duration · scope · who owns the revenueFollows the installed base and operating hours · revenue is not automatic without a contract
Gas-turbine blade
SUPPLY SIDE · potential supply response

Supply is starting to respond outside the incumbent OEMs too

SpaceX
In-house turbine components

SpaceX is building a gas-turbine blade-and-vane foundry in Bastrop, Texas. Elon Musk says blade and vane casting is the limiting factor in turbine production and claims in-house casting could cut delivery delays by as much as 18 months · this is a company claim, not verified production capacity.53

Parallax
New small-turbine entrants

Parallax is developing a 10 MW-class data-center turbine using 3D printing to reduce part count · it has raised USD 117m · prototype targeted for end-2026, testing in 2027, first customer deliveries in 2028 · not counted as supply before validation.54

SpaceX bringing turbine components in-house and new turbine entrants could shorten the bottleneck’s shelf life · if turbines loosen sooner than expected, some demand that spilled into engines can unwind sooner too · neither is verified production capacity yet.

Why incumbents remember the last cycle

When gas-turbine demand collapsed in 2017–18, manufacturers were caught with expansion underway and responded with large layoffs.55 Siemens Energy’s CEO has said the company is managing capacity very carefully to avoid creating an oversupply that could hurt it over the next decade.56 Doosan Enerbility faces the same strategic tension: capacity added during a shortage can dilute pricing power once competitors expand too.51

The demand-side variables

Kyobo Securities reviewed 150 data-center projects that faced local opposition. Among the cases where power was a stated issue, 91% were canceled or halted. That is not a cancellation rate for the U.S. data-center market as a whole.49 In 1Q26, 75 U.S. data-center projects worth USD 130bn were halted or delayed amid community opposition.2 The IEA notes that data centers fill gradually, making peak-load needs uncertain and creating a risk of over-connection.57 On the other side, Caterpillar’s CEO says no customer is slowing order pace yet. In the same answer, however, he stressed that capacity expansion is not based on data centers alone, citing oil and gas—especially gas compression—plus mining and marine demand, and adding that the oil-and-gas backlog is nearly twice the year-earlier level.50

PAGE 07 · TAKEAWAY

If turbine lead times fall, growth in new engine orders can slow. Engine makers’ own capacity additions may move pricing before that happens.

Operation of the installed engine base and service revenue are separate questions. Track new orders and installed units as two different datasets.

NEXT08 What to check next
What to check nextPage 08
NextWhat to check next

A Warning Signal Is Not
a Broken Thesis

One quarter can move simply because of contract timing · falsification requires a more structural change

The three variables to track are new orders, lead times, and capacity. The next round of earnings and regulatory milestones should tell us which way each is moving.

WARNING · signals to watch

One print is not enough

  • One quarter of weaker engine / power-equipment orders
  • One quarter of lower engine-segment margin
  • A monthly turn lower in newbuilding prices
  • Delay at an individual data-center project
CHECK · core assumptions

These would force us to rewrite the thesis

  • Large-scale cancellation of gas-turbine slot reservations · sharp drop in conversion to firm orders
  • A rapid compression in engine and turbine lead times
  • A turn lower in new-order economics, including backlog margin
  • Failure by Korean engine makers to convert lines for power generation · delays in licensing or certification
  • Electrical integration, permitting, and EPC timelines becoming longer than engine lead times, so engine-slot scarcity no longer sets the project schedule
Next checkpointsOctober–December
Early October Clarksons Research
September orders · newbuilding prices

Does the Korea + China contract pace still point above the 2007 record?

10.12 PJM
Requested effective date for BYONC / IRAS

Check for FERC approval · does the pathway for large loads to bring new generation become an effective rule?46

10.27 Wärtsilä
3Q earnings

Energy-equipment backlog margin · delivery lead times · data-center orders.36

10.28 GE Vernova
3Q earnings MOST IMPORTANT

20:30 KST · path toward GE Vernova’s year-end target of 125 GW+ backlog plus reservations · conversion of reservations to firm orders · share of contracting now reaching 2031 deliveries.5

Late October Korean engine makers
3Q earnings · date TBD

Engine-segment margin and backlog · new power-generation order disclosures.

11.03 Wärtsilä
Capital Markets Day

How capacity is allocated after the Vaasa expansion · whether Wärtsilä restates priorities between Energy and Marine.36

11.23 New Mexico
Oracle Project Jupiter air-permit decision deadline

A live test of whether permitting, rather than equipment, sets the commercial-operation date.12

12.04 IMO
NZF special session resumes (date to be confirmed at MEPC 85)

Adoption and any dilution · another delay would weaken the incentive to shift marine orders toward DF engines.

Date TBD Hanwha Engine
Power-engine license · first data-center order

Everllence 35/44G agreement and whether group-linked orders emerge.

UPDATE PLAN · Refresh FIG 01-1, 04-3, and 07-1 after GE Vernova’s Oct. 28 3Q results and the Dec. 4 IMO outcome.

BOTTOM LINE · back to the numbers
WHERE

Parts of the four-stroke medium-speed line—and the testing and component supply chain around it. That is where shipboard-generator orders meet data-center power-plant orders. Two-stroke propulsion engines and high-speed gensets from Caterpillar, INNIO, Cummins, and others are outside this scope.

HOW MUCH

Hanwha Engine · about 360 MW of estimated 2027 data-center headroom(SK Securities estimate) · typical buyer project size is 250–400 MW. At HD Hyundai, the two demand pools can still overlap on the existing HiMSEN base before the new Onsan plant—3 GW/year of installed capacity—is completed in May 2028.

WHEN

Engine expansions: 2028–29 · gas-turbine lead-time normalization: 2031–32(SK Securities forecast). Caterpillar moves earlier: its restarted 10 MW-class medium-speed engine begins shipping in 4Q26 and is planned to ramp to about 1.5 GW over 18 months. Engine supply can loosen first, changing bargaining power before turbines normalize.

WHAT TO COUNT

New orders · installed base · service contracts—count them separately. They become revenue at different times, and the revenue can accrue to different companies.

Glossary · 12 terms worth knowing Expand +Collapse −
Two-stroke vs. four-stroke engines
A two-stroke engine fires once per crankshaft revolution; a four-stroke fires once every two revolutions · large merchant-ship propulsion typically uses low-speed two-strokes, while power generation uses medium- and high-speed four-strokes
Medium-speed vs. high-speed
A classification by engine rpm · medium-speed engines run at several hundred rpm, while high-speed engines run at 1,000 rpm or more · in data centers, high-speed units are typically smaller gensets, while medium-speed engines are used in larger power plants
HiMSEN
HD Hyundai’s proprietary four-stroke medium-speed engine brand · used in shipboard generation and land-based power plants
Dual-fuel (DF) engine
An engine that can burn both LNG and conventional marine fuel · currently the main marine-engine response to carbon regulation
Aeroderivative vs. combined cycle
An aeroderivative is a gas turbine adapted from aircraft-engine technology, typically in the tens-of-MW range · combined cycle adds a steam turbine driven by gas-turbine exhaust heat
Slot reservation
An agreement that holds a place in the production queue before a firm order · it can convert to a firm booking or be canceled
On-site generation · BYOG
Power generation located on or next to the data-center site · BYOG means bringing dedicated generation and connecting it alongside the load
N+1
N+1 redundancy: keep one more unit than the number required · the larger each unit is, the heavier the spare-capacity burden
UPS
UPS: uninterruptible power supply · batteries or similar systems absorb momentary outages and fast load swings before generators can respond
DWT · CGT
DWT measures how much weight a ship can carry; CGT is a standardized tonnage that adjusts for vessel complexity and is used to compare shipyard workload
NZF · Net-Zero Framework
The IMO’s proposed carbon-pricing framework for international shipping · ships pay when fuel greenhouse-gas intensity exceeds the target
LTSA · O&M
LTSA / O&M: long-term service agreements plus operations and maintenance · revenue that can continue after the engine sale
Source ledger · evidence behind the numbers Expand +Collapse −
  1. 01
    ERCOT · “PUCT approves ERCOT’s Batch Zero” · 2026.06.18 · coordinated interconnection review for large loads of 75 MW or more · large-load requests above 438,000 MW · 89% data centers · Original ↑ Back to text
  2. 02
    SK Securities · “Shipbuilding · Conditions for Re-rating: Data Centers & Naval Vessels” (Han Seung-han), 2026.09.17 · 136 pp. · roughly five years from U.S. AI data-center interconnection request to commercial operation (underlying source not specified) · heavy-duty gas-turbine lead time about 5–6 years · aeroderivatives up to 3 years · four-stroke engines 18–24 months (high-speed 1–2 years; medium-speed 2–3 years) · engine/turbine efficiency and part-load comparison · major gas-turbine supply normalization 2031–32 · HD Hyundai land-based capacity 4.0 GW (existing Yeongam 0.7 GW → 1.0 GW + new Onsan 3.0 GW) · Hanwha Engine estimated 2027 data-center headroom about 360 MW · service interval 3 years · 25-year service revenue about 2.5× engine sales (estimate) · high-speed share of data-center engine orders · AEG annual deliveries (11 units each in 2028–30) · 75 U.S. projects worth USD 130bn halted or delayed by community opposition in 1Q26 · printed page numbers are one lower than PDF page numbers ↑ Back to text
  3. 03
    LBNL · “Queued Up: 2026 Edition” · median 61 months from interconnection request to commercial operation for projects entering service in 2025 · applies to generation and storage, not load interconnection requests such as data centers · Original ↑ Back to text
  4. 04
    DS Investment & Securities · “AIDC Power, Act II: How Regulation Is Rewriting the Market” (Ahn Joo-won), 2026.09.29 · 35 pp. · U.S. data-center on-site generation share 10% in 2026 → 30% in 2030 (citing BCG / Goldman Sachs) · Virginia Tier 4 requirement for new diesel generators from 2026.07.01 · Oracle Project Jupiter 2.5 GW fuel-cell conversion, permitting paused and later resumed ↑ Back to text
  5. 05
    GE Vernova · “Second Quarter 2026 Financial Results,” 2026.07.22 · Gas Power equipment backlog 44→53 GW · slot reservations 56→63 GW · total 100→116 GW · year-end target at least 125 GW · manufacturing capacity 20 GW/year → 24 GW in 2028 → 30 GW in 2030 · the press release’s “more than USD 5bn of data-center orders” appears in the Electrification discussion and is separate from the gas-turbine metrics, so it is not used in the body · Original · SEC / Utility Dive, 2026.07.23 · currently accepting reservations for 2031 deliveries · Article / 3Q earnings webcast 2026.10.28, 07:30–08:30 EDT (20:30 KST) · IR calendar ↑ Back to text
  6. 06
    Doosan Enerbility · Seoul Shinmun · 2026.03.06 · seven 380 MW-class gas turbines for a U.S. company · 12 cumulative units with the same customer · one unit per month from May 2029 · Article · two units in October 2025 and three in December 2025 · Doosan Newsroom ↑ Back to text
  7. 07
    Siemens Energy · “Earnings Release Q3 FY2026,” 2026.08.05 · quarterly orders EUR 17.9bn · Original / Utility Dive, 2026.08.10 · gas-turbine backlog 69 GW · lead time above 3 years · heavy-duty capacity roughly 35 units/year +15 units in 2027 · medium-size capacity 80/year → about 100/year in 2028 · Article / Turbomachinery Magazine, 2026.08.06 · Gas Services orders +61.9% · Article ↑ Back to text
  8. 08
    Utility Dive · 2026.08.13 · Mitsubishi Heavy Industries heavy-duty gas-turbine backlog 35 GW (23 GW a year earlier) · capacity expansion to 2× 2024 level in progress · Article ↑ Back to text
  9. 09
    Wärtsilä · 2026.04.16 · first data-center application of the 34SG · 412 MW in Ohio · commercial operation targeted for early 2028 · Original · SK Securities cites the schedule as a “21-month” example ↑ Back to text
  10. 10
    Dell · JERA · RHAELM · 2026.10.01 · up to 400 MW of AI infrastructure at JERA’s Chiba thermal power plant · behind-the-meter power from existing generation · “years ahead of a conventional grid-connected development schedule” · MoU · expected investment above USD 15bn · target operation around 2028 · Data Centre Magazine ↑ Back to text
  11. 11
    SK Securities · “Higher for Longer, AI Differentiation,” 2026.09.28 · force-majeure notice at Oracle’s 2.45 GW New Mexico campus · gas-pipeline completion delayed to 2027.02.01 · fuel-cell air permit not issued ↑ Back to text
  12. 12
    TechCrunch · 2026.09.24 · Oracle notified the Blue Owl side of force majeure on the 2.45 GW New Mexico campus · Energy Transfer pipeline delayed to 2027.02.01 · air-permit decision deadline Nov. 23 · Oracle: “Project Jupiter remains on our planned schedule” · Article · WSJ and Barron’s also reported the same issue ↑ Back to text
  13. 13
    Wärtsilä · Schneider Electric · Stanley Consultants · Wärtsilä press release, 2026.09.30 21:31 local time (UTC+2) · 2026.10.01 KST · Wärtsilä press release (Cision) · U.S. data-center “Generator-to-Chip” power collaboration · engine power plants · electrical equipment, automation, and power management · design, permitting, construction management, and commissioning oversight · “can accelerate project schedules compared to traditional, sequential delivery models” · “Power has become the schedule” · no capacity or quantified schedule reduction disclosed · PR Newswire ↑ Back to text
  14. 14
    GE Vernova · LM2500 product page · “can be installed in less than 30 days” for the XPRESS package · Original ↑ Back to text
  15. 15
    GE Vernova · 2025.07.22 · 29 cumulative LM2500XPRESS units for Crusoe · “nearly 1 GW” · 19 units in June 2025 + 10 units in December 2024 · “five-minute fast start capability” · Original ↑ Back to text
  16. 16
    Schneider Electric · blog, 2026.09.15 · “AI workloads are unpredictable, triggering power surges in milliseconds” · “The UPS absorbs these fluctuations first” · Original ↑ Back to text
  17. 17
    Langley Holdings(Bergen Engines) · Crusoe · 2026.06.03 · about 750 MW = roughly 438 MW under contract + 310 MW under LOI · 27 × 12.5 MWe + 20 × 5 MWe · “phased through 2027” · “continuous on-site baseload power generation” · includes Piller SHIELD-X dynamic power conditioning · Original · Crusoe ↑ Back to text
  18. 18
    DS Investment & Securities · “[Shipbuilding] Engines: The Semiconductors of the Sea” (Kim Dae-sung), 2026.09.29 · 54 pp. · Korea + China merchant-ship contracts 173m DWT through end-August 2026 · 2007 full-year 194m DWT · 2026 full-year estimate 260m DWT · 2025 two-stroke engine order share: Korea 56%, China 36% (media compilation) · private Chinese yards’ Korean-engine orders above KRW 900bn in 2025 · Korea/China engine-performance comparison table based on manufacturer data · HD Hyundai capacity mix 3.0 GW in 2025 → 7.2 GW in 2030 · Hanwha Engine two-stroke slots sold out through 2028 · backlog: HD Hyundai Heavy Industries KRW 12tn · Hanwha Engine ASP chart · carbon-cost table assuming a 50% softened NZF (DS calculation) · U.S. strategic merchant fleet roughly 80 vessels → 250 · several numerical inconsistencies within the report (e.g., three-company total KRW 20.4tn versus KRW 19.4tn from listed components) ↑ Back to text
  19. 19
    Clarksons Research · Sisa Journal · 2026.09.04 · global orderbook 216.43m CGT at end-August (China 67% · Korea 18%) · Newbuilding Price Index 186.34 at end-August · Article ↑ Back to text
  20. 20
    MediaPen · 2026.07.01 · 12 of HD Hyundai Marine Engine’s 15 first-half orders came from Chinese shipyards · Article ↑ Back to text
  21. 21
    Financial News · citing Yuanta Securities · 2026.08.28 · China share of Hanwha Engine backlog 33%→49% · two-stroke production capacity 5.3m hp · Article ↑ Back to text
  22. 22
    IMO · MEPC/ES.2, October 2025 · vote to adjourn NZF adoption for one year rather than adopt: 57 in favor, 49 against · Original / DNV · Commentary ↑ Back to text
  23. 23
    IMO · MEPC 84 (2026.04.27–05.01) outcome · intersessional working groups 2026.09.01–04 and 11.23–27 → MEPC 85 on 11.30–12.03 → resumed special session on 12.04, date to be confirmed at MEPC 85 · Original ↑ Back to text
  24. 24
    Shipping Telegraph · September 2026 · September intersessional working group ended without agreement · U.S. and Saudi opposition continued · Article ↑ Back to text
  25. 25
    Wärtsilä · “All engine types in Wärtsilä’s portfolio are manufactured at STH” · 2026.02.04 Vaasa capacity +35% (about EUR 140m, operational 1Q28) · Original · 2026.05.26 additional +30% (about EUR 90m, operational 1Q29) · cumulative +65% versus 2025 · expansion tied to Energy and Marine demand and the associated supply chain · Original ↑ Back to text
  26. 26
    Wärtsilä · “Highlights from the CEO strategy call Q3 2026,” 2026.09.29 · “accounting for less than half of Wärtsilä’s Energy equipment order backlog” · “We do not have slot reservation agreements with individual customers” · “we allocate capacity for firm orders based on a combination of commercial opportunities, strategic priorities, customer relationships and geographic diversification” · expansion phases in during 2028–29 · Original ↑ Back to text
  27. 27
    HuffPost Korea · based on half-year report · 2026.09.11 · HD Hyundai Heavy Industries engine utilization 113% in 2Q · Engine & Machinery operating margin 18.3% in 2025 → 21.1% in 1Q26 → 24.8% in 2Q26 · Article ↑ Back to text
  28. 28
    Media compilation · HD Hyundai Marine Engine = former STX Heavy Industries (Changwon) · renamed 2024.07.30 · Bizwatch · Hanwha Engine = former HSD Engine (Changwon) · launched 2024.02.28 · Gyeongnam Shinmun · Hyundai Engine plant in Yeongam (Daebul Industrial Complex) opened in October 2022 · Mokpo Chamber of Commerce & Industry · “The main Ulsan plant will serve marine engines, while the new plant and Yeongam facility will serve land-based power” · EToday ↑ Back to text
  29. 29
    HD Hyundai Heavy Industries filings · media reports · 2026.04.22 single-sales/supply contract · Aperion Energy Group Holdings · KRW 627.1bn · contract period 2026.04.21–2030.10.21 · 684 MW · 20 MW-class HiMSEN engines · Filing alert · Asia Economy · engine count and annual delivery schedule not disclosed in the filing ↑ Back to text
  30. 30
    HD Hyundai Heavy Industries press release · 2026.08.09 · U.S. Corban Energy Group 1,000 MW · KRW 956.0bn · 9.6 MW-class HiMSEN · largest power-engine contract in company history · contract dated 2026.08.07 · Reprint ↑ Back to text
  31. 31
    MoneyToday · 2026.09.10 · HD Hyundai Heavy Industries power-engine plant · KRW 833.6bn investment · Onsan, Ulsan · 3 GW/year · construction starts 1Q27 · completion May 2028 · Article ↑ Back to text
  32. 32
    HD Hyundai Heavy Industries new-facility investment filing · media reports · 2026.09.10 · investment period 2026.09–2028.05.31 · construction starts 1Q27 · completion / start-up May 2028 · assembly, commissioning, crankshaft machining, and block-casting equipment · 3 GW/year · HiMSEN 7.2 GW target in 2030 · Filing roundup · EToday · Herald Economy / Shinhan Securities research citing the Sept. 10 expansion conference call · HiMSEN total 3.0→7.2 GW · land-based power 0.7→4.0 GW (2025→2030; cover figure) · Article ↑ Back to text
  33. 33
    Pinpoint News · citing brokerage research · 2026.09.19 · Hanwha Engine Changwon four-stroke medium-speed engine plant completed 2026.08.19 · 900 MW/year (180 × 5 MW) · pursuing license for Everllence 35/44G power-generation engine (not yet final) · Article ↑ Back to text
  34. 34
    Herald Economy · 2026.08.25 · HD Hyundai Marine Engine backlog KRW 1.6705tn at end-1H · operating margin 18.9%→24.4% · Article ↑ Back to text
  35. 35
    HuffPost Korea · based on half-year report · 2026.09.29 · Hanwha Engine backlog KRW 2.5472tn at end-2023 → KRW 4.1427tn at end-2025 → KRW 5.9789tn at end-June 2026 · dual-fuel share 83% · Article ↑ Back to text
  36. 36
    Wärtsilä · “Half-year Financial Report January–June 2026,” 2026.07.21 · “the gross margin of the Energy equipment order book has improved by more than 500 basis points” since early 2025 · Energy backlog more than doubled · “the existing order book will generate sales that are distributed further into the future” · Original / 2026 financial calendar · January–September interim report 2026.10.27 · Capital Markets Day 2026.11.03 · IR · Reposted financial-calendar notice ↑ Back to text
  37. 37
    Power Engineering · April 2026 · GE Vernova 1Q earnings call · pricing on new gas-turbine orders running above 4Q25 levels · Article · no specific uplift used in the body because the original management wording had not been independently checked ↑ Back to text
  38. 38
    Enerflex · 2026.10.01 · contract with a North American data-center developer to design, engineer, fabricate, and assemble roughly 450 MW of behind-the-meter natural-gas generation · deliveries begin in 2027 and finish in 2028 · approved 2026 capex of about USD 15m plus roughly USD 85m more, mostly in 2027 · engine supplier undisclosed · Enerflex official release · StockTitan reprint · CP24 ↑ Back to text
  39. 39
    ZDNet Korea · NewsPim · 2026.05.18 · HD Hyundai Marine Solution–AEG MoU covering long-term maintenance, service, and operations for 33 data-center power engines · pursuing LTSA and O&M agreements · ZDNet Korea · NewsPim ↑ Back to text
  40. 40
    Hanwha · Korea Economic Daily · Hanwha Engine profile: “long-term service agreements that are valid for the engine’s lifetime” · Hanwha · 2025.02.27 five-year LTSA covering 27 Pan Ocean vessels · KRW 19.6bn · Korea Economic Daily ↑ Back to text
  41. 41
    FERC · Fact Sheet, 2025.12.18 · FERC directed PJM to create a new transmission service for co-located loads · Original ↑ Back to text
  42. 42
    PJM · Inside Lines, 2026.01.16 · board plan for integrating large loads · pathway for loads to bring new generation · Original ↑ Back to text
  43. 43
    Oregon Public Utility Commission · OPB · 2026.07.07 · PGE rates for data centers and other large loads above 20 MW increased 29.7% · residential rates reduced · Article · Press release ↑ Back to text
  44. 44
    PJM Inside Lines · Utility Dive · RTO Insider · 2026.09.29–30 · FERC accepted PJM’s Reliability Backstop Procurement proposal but suspended its effective date for five months, until 2027.02.28 · subject to refund conditions and the outcome of further proceedings · PJM: “the RBP process will not begin on Sept. 30” · PJM Inside Lines · further proceedings on cost allocation, transmission-owner withdrawal rules, and collateral requirements · PJM postponed the 9.30–10.21 procurement auction · Utility Dive · RTO Insider · Docket ER26-3380 ↑ Back to text
  45. 45
    FERC · Commissioner Rosner’s · See’s Concurrence · ER26-3380 · 2026.09.29 · See 「Customers that drive new costs should bear appropriate responsibility for them」 「Existing customers should not be left paying costs attributable to new demand」 · See concurrence · Rosner 「PJM will assign costs to those responsible (i.e. to the zones with data center growth)」 · Rosner concurrence ↑ Back to text
  46. 46
    PJM · POWER Magazine · 2026.08.20 · BYONC (Bring Your Own New Capacity) and IRAS filed with FERC on 2026.08.13 (ER26-3515) · PJM requested effective date 2026.10.12 · FERC approval still pending as of Oct. 2 · IRAS applies to new large loads of 50 MW or more entering service on or after 2027.06.01 · capacity must be “new and not repackaged” · Article · Data Center Knowledge ↑ Back to text
  47. 47
    Virginia Code § 10.1-1322.6 · data-center permit applications filed on or after 2026.07.01 · each generator set must meet-equivalent or tighter emissions limits · Tier 4 equivalent = SCR, diesel oxidation catalyst (DOC), particulate filter (DPF), or equivalent controls · Statute · Commentary ↑ Back to text
  48. 48
    Greenberg Traurig · Microgrid Media · September 2026 · commentary on Virginia Executive Order 22 (2026.09.18) · new data centers at or above 25 MW excluded from fast-track permitting and state support · review of emergency-generation equipment ordered · not a ban or direct restriction on gas generation · Commentary · Article · DS Investment & Securities’ table label “gas generation restricted above 25 MW” differs from this legal commentary ↑ Back to text
  49. 49
    Kyobo Securities · “Are Data Centers Really Not Being Built?” (Kim Kwang-sik), 2026.09.15 · analysis of 150 opposed projects · among opposed cases where power was an issue, 91% were canceled or halted · 7% moved into construction · New York executive order dated 2026.07.14 pauses permitting for data centers of 50 MW or more for up to one year ↑ Back to text
  50. 50
    Manufacturing Dive · 2026.08.05 · Caterpillar 2Q power-generation retail sales +72% · backlog USD 72bn · power customers ordering out to 2030 · restart of 10 MW-class medium-speed gas engine for 1.5 GW of capacity · CEO: “nobody is slowing down” · same answer also cited oil & gas (gas compression), mining, and marine demand and said the oil & gas backlog was nearly 2× year earlier (2Q earnings call 2026.08.04 · Transcript · Summary) · Article / 2026.05.01 · large reciprocating-engine capacity to reach 3× 2024 level · Article / 10 MW-class medium-speed gas reciprocating engine restarted after production stopped in 2022 · first order secured · first shipment 4Q26 · ramp to 1.5 GW over 18 months · Utility Dive 2026.08.11 ↑ Back to text
  51. 51
    NewsPim · 2026.09.02 · Doosan Enerbility gas-turbine capacity 8 units/year → 12 units in 2028 · pricing-power dilemma of expanding during a shortage · Article ↑ Back to text
  52. 52
    Rystad Energy · 「Gas Turbine Report H2 2026」 2026.09.14 · 「Gas turbine and reciprocating engine orders hit a record 100 GW last year, 30% above what OEMs could actually deliver」 · 「That gap hasn’t closed」 · 「oversupply risk is building as new entrants target the 20-50 MW segment」 · Original ↑ Back to text
  53. 53
    Tom’s Hardware · 2026.08.30 · SpaceX insourcing gas-turbine blade and vane casting · Musk X post dated 8.29: “The limiting factor for nat gas turbine production is casting the blades & vanes” · claims up to 18 months of schedule compression · feasibility uncertain · Article · FT also reported the same development ↑ Back to text
  54. 54
    WSJ (reprinted by Yahoo Finance) · 2026.09.24 · Parallax 10 MW-class 3D-printed gas turbine · raised USD 117m · prototype by end-2026 · testing in 2027 · first customer deliveries in 2028 · Article ↑ Back to text
  55. 55
    Heatmap News · 2025.02.26 · 2017–18 collapse in gas-turbine demand and layoffs · manufacturers remain cautious about expansion · Article ↑ Back to text
  56. 56
    Bloomberg · reprinted by EnergyNow · 2026.08.05 · Siemens Energy CEO: capacity is being managed “very sensitively” to avoid oversupply over the next decade · Article ↑ Back to text
  57. 57
    IEA · “Key Questions on Energy and AI” · data-center electricity demand 950 TWh in 2030 (central case) · uncertainty around peak load and risk of over-connection · Original ↑ Back to text

This report is research on the supply-demand structure of power-generation and marine engines and gas turbines · it is not a recommendation to buy or sell any security or asset · broker estimates and manufacturer claims are identified as such and are not treated as established fact · reporting periods differ across overseas companies · broker estimates—including the Korea/China order table, four-stroke headroom, service-revenue multiple, carbon-cost calculation, and AEG annual unit schedule—follow the assumptions in those source materials · public information checked through 2026.10.02 20:00 KST.